Anonymised sample assessment

The cheapest quote is not always the lowest-cost decision.

This illustrative assessment shows how RESET Supply turns supplier responses into a documented sourcing decision. Names and figures are anonymised; the structure reflects our working method, not a customer quotation.

Category

Outdoor aluminium & glass system

Target market

DACH commercial project

First-order scenario

€85k target purchasing value

Decision window

Supplier recommendation within 3 weeks

01 · Supplier comparison

Three viable factories. One defendable recommendation.

Decision factorSupplier ASupplier BRecommendedSupplier C
EXW price index100 · lowest108103
Manufacturing fitMediumStrongStrong
Engineering responseWeakStrongMedium
Documentation readinessMaterial gapsStructuredPartial
Lead-time promise11 weeks12 weeks10 weeks
Payment terms40 / 6030 / 7050 / 50
Packaging riskHighLowMedium
Overall execution riskHighLowMedium
Supplier B costs more at factory gate, but has the strongest engineering response, cleaner documentation, lower packaging risk and better commercial terms. That makes the total project risk—and the probable landed cost—lower.

02 · Landed-cost scenario

Compare what arrives—not just what leaves the factory.

Illustrative scenario only. Freight, tariff classification, duties, taxes and compliance costs must be validated for the actual product, route and Incoterm.

Supplier B product value€73,500
Samples & tooling€1,800
Export packaging€2,200
China inland & export handling€1,700
Freight & insurance assumption€5,200
Inspection & verification€1,200
Estimated duty provision€4,400
Project contingency€2,000
Estimated landed cost before import VAT€92,000

03 · Priority risk register

The decision is conditional—not blind.

01 · Compliance boundary

Confirm the applicable EU product route, importer responsibilities and exact document scope with qualified specialists before order release.

02 · Drawing & tolerance freeze

Close interface dimensions, finish tolerances and approved materials before requesting final quotation.

03 · Transit protection

Approve export packaging, loading method and damage-liability process before mass production.

04 · Commercial control

Fix tooling ownership, golden-sample status, milestone payments and change-control rules in writing.

04 · Recommendation

Proceed with Supplier B—subject to four release gates.

Engineering drawing freeze
Material and document review
Golden sample approval
Packaging and inspection plan signed off

A real assessment uses your drawings, quantities, destination, compliance requirements and supplier evidence.